Marin Independent Journal



Wetlands work could lead to breakthrough
By Con Garretson
IJ reporter


Sunday, January 23, 2005 - The U.S. Army Corps of Engineers is exploring new ways to store and deliver dredged bay materials for the Hamilton Wetlands Restoration Project.

The idea being looked at is temporarily redumping dredged material from elsewhere in the bay back into the bay rather than directly pumping it from barges, an alternative that might cost less, be more efficient and be better for the environment.

"Dumping in the bay has been such a hot-button issue for so long that it initially seems to be counter-intuitive to dump the materials again," said Tom Gandesbery, a project manager with the California Coastal Commission, which is working with the Army Corps on the project.

"I don't think it's been done this way anywhere else in the country," he said. "It was one of the rare instances where the Army Corps took a look at the process and thought there may be a better way to do things."

The dredged materials are needed to help rebuild the former Hamilton wetlands.

Gandesbery said selection of one of the redumping methods could lead to the closure of one or two of three bay sites nearby where dredged materials are currently dumped.

At least four new alternative methods will be explored as part of an environmental review process, including a contained storage basin, a semi-contained basin, uncontained storage on the bay floor and a combination of the proposed method and the approved hydraulic off-loader method.

There are no firm cost estimates for the storage options, which include building an underwater berm and a fully enclosed storage basin, Gandesbery said.

A review of the storage options will culminate in a report this summer that will be the subject of public review before an option is selected by the Army Corps.

As part of the process, an initial public scoping meeting is scheduled for 7 to 9 p.m. Wednesday at the Bay Model at 2100 Bridgeway in Sausalito. Public comment on the environmental impacts will be taken.

The project will convert nearly 1,000 acres of Novato's developed bayside lands, consisting of the runways and antenna fields of the former Hamilton Field military base, back into tidal and seasonal wetlands. The possible addition of land at adjacent Bel Marin Keys would expand the wetlands' size to 2,500 acres.

The original plan was to use a San Pablo Bay-based hydraulic off-loader to handle environmentally acceptable dredged materials from the Port of Oakland and other regional locales to be stored five miles off Hamilton Field, from which the materials would be pumped. The offshore pumping is necessary because of shallow conditions.

Gandesbery said the possible changes were prompted by "the cost to the taxpayer and the efficiency of doing the project, which also has an environmental benefit.

"There would be a lot less air pollution by using smaller equipment that could run continuously, over turning larger equipment off and on," he said. "There would be less diesel emissions, where most of the pollution comes from."

The original method would necessitate the coordination of large barges making the direct transfer through submerged pipelines, while the new options would allow smaller barges to also dump at different times and for the pumping to take place continuously rather than in spurts.

The proposed methods would have to receive permits and would likely not be put into use until 2007. Gandesbery said initial restoration work scheduled for this fall with Port of Oakland dredgings will go forward using the already approved direct-pumping process.

Work on the airfield portion is expected to take five years, while the overall project, including the antenna fields and the possible Bel Marin Keys land, could take up to 19 years.

The initial work would include 2.5 million cubic yards of materials, and up to 23 million cubic yards would be used for the remainder of the project.

The overall project cost is estimated to exceed $100 million, 75 percent of which would be paid by the federal government and the remainder by the state.


Contact Con Garretson via e-mail at cgarretson@marinij.com

http://www.marinij.com/Stories/0,1413,234%257E24407%257E2669831,00.html?search=filter

Copyright and permissions